The binding constraint — the boundary this site runs into first — is timeline, with a gap of 50 % ◌ derived. The runner-up is hardware at 37.2 % ◌ derived, a margin of 12.8 % ◌ derived.
Everything this site needs can be had — just not yet. Grid connection, permits, construction and deliveries stack into one long schedule, and no revenue flows until the last step clears. Waiting itself is the cost: every month of schedule is a month of financing paid with nothing earned.
Timeline binds at 50 % ◌ derived. The deployment schedule runs 24 months ◌ derived, with the utility queue at 24 months ◌ derived inside it. Revenue starts when the last gate clears; every month of schedule is a month of carry.
In this market, supply and demand are in balance: the facility can serve its demand at target utilisation across the planning horizon. The constraint register files this state under the code R1 ◌ derived.
Whether that is acceptable is a judgment this model does not make.